Construction Update from the Bureau of Environmental Services

Comments Off

FROM: Bureau of Environmental Services (BES), City of Portland
DATE: April 9, 2010 — Email project update #19
BES will return about April 19th to Burnside to finish laterals and storm inlets between 20th and 22nd.  This should take 2-4 weeks.
Two week look ahead
  • SE Ankeny, 13th to 16th – work will continue for another week on service laterals from 13th to 16th.  No through traffic during work hours, local access only.
  • SE Ash, 13th to 18th –Lateral and storm inlet work will continue for 2-4 weeks—traffic detoured around work zone.
  • SE Pine, 10th to 17th – Inlet work at intersections—traffic detoured around work zone.
  • SE 10th & Oak Drop Shaft – The intersection is completely closed in all directions, and will remain so for several months.
Paving work is weather dependant, stay tuned.
Please feel free to forward this email to tenants, customers, vendors, managers, or anyone affected by the work.
We will add anyone to the distribution list who requests it.  This can also be done on the BES website at:
http://www.portlandonline.com/bes/oakproject
David Allred
Community Outreach and Public Involvement
Bureau of Environmental Services
Desk: 503-823-7287